feat(crewing): Phase 5a — verification queue (flagged)
First slice of Phase 5 (verification + appraisal). The office queue for verifying
site-entered records, per Crewing-Implementation-Spec §8.11/R11. Stacks on 4c.
Behind NEXT_PUBLIC_CREWING_ENABLED.

What's in
- Schema: CrewActionType += RECORD_VERIFIED/RECORD_REJECTED (migration
  crewing_verification_actions). No model changes — SeafarerDocument/BankDetail/
  EpfDetail already carry verificationStatus + verifiedById (3b/4a).
- Actions (crewing/verification/actions.ts): verifyDocument (verify_site_records —
  MPO/Manager) and verifyBankEpf (verify_bank_epf — Accounts) set
  verificationStatus VERIFIED/REJECTED + verifiedById; rejection requires remarks;
  each writes a CrewAction. Already-decided records are guarded.
- Screen: /crewing/verification — role-aware (MPO: pending documents with expiry
  flags; Accounts: pending bank/EPF), Verify / Reject-with-remarks. Leave is not
  here (Manager approval, R11). Verification added to nav (MPO + Accounts + SU, §7).

Tests & docs
- Integration: verification.test.ts (6) — doc verify/reject + already-decided
  guard, bank/EPF verify, permission gating (Accounts can't verify docs, MPO can't
  verify bank/EPF). type-check clean; full unit (241) + integration (201) green
  (verified with RESEND_API_KEY unset, mimicking CI).
- CLAUDE.md updated.

Deferred (per decision): PPE / next-of-kin verification gates.

Co-Authored-By: Claude Opus 4.8 (1M context) <noreply@anthropic.com>
2026-06-22 21:59:31 +05:30
..
admin-ranks.test.ts feat(crewing): foundations — SITE_STAFF role, ranks reference data + admin (flagged) 2026-06-22 13:26:04 +05:30
applications.test.ts feat(crewing): Phase 3b — recruitment pipeline (flagged) 2026-06-22 18:49:12 +05:30
approval-actions.test.ts test(integration): green the last 3 behavioural-drift tests (108/108) 2026-06-21 02:39:41 +05:30
approved-this-month.test.ts fix(dashboard): count all POs approved this month, not just current MGR_APPROVED 2026-06-19 12:07:53 +05:30
cancel-supersede.test.ts feat(po): cancel POs (manager/superuser) + optional supersede link (#53) 2026-06-21 12:20:54 +05:30
candidates.test.ts feat(crewing): Phase 3a — candidates / talent pool (flagged) 2026-06-22 18:23:01 +05:30
company-branding.test.ts feat(po): per-company logo, stamp & brand bar on exported POs 2026-06-21 01:17:23 +05:30
company-crud.test.ts test(companies): cover createCompany/updateCompany actions 2026-06-21 02:05:32 +05:30
confirm-receipt.test.ts test(integration): repair stale integration suite (wip: 97/108) 2026-06-21 02:34:07 +05:30
create-po.test.ts test(integration): repair stale integration suite (wip: 97/108) 2026-06-21 02:34:07 +05:30
crew-records.test.ts feat(crewing): Phase 4a — crew records & profile + PPE (flagged) 2026-06-22 19:27:21 +05:30
crewing-admin.test.ts feat(crewing): admin crew management — direct placement, CRUD, strength config 2026-06-22 21:23:31 +05:30
discard-po.test.ts test(integration): repair stale integration suite (wip: 97/108) 2026-06-21 02:34:07 +05:30
helpers.ts test(integration): green the last 3 behavioural-drift tests (108/108) 2026-06-21 02:39:41 +05:30
import-api.test.ts test(integration): repair stale integration suite (wip: 97/108) 2026-06-21 02:34:07 +05:30
leave-attendance.test.ts feat(crewing): clash detection by required strength (Option A) 2026-06-22 21:14:21 +05:30
manager-po-creation.test.ts test(integration): repair stale integration suite (wip: 97/108) 2026-06-21 02:34:07 +05:30
onboarding.test.ts feat(crewing): Phase 3c — onboarding (flagged) 2026-06-22 19:12:53 +05:30
payment-actions.test.ts test(integration): green the last 3 behavioural-drift tests (108/108) 2026-06-21 02:39:41 +05:30
products-search.test.ts test(integration): repair stale integration suite (wip: 97/108) 2026-06-21 02:34:07 +05:30
requisitions.test.ts feat(crewing): Phase 2 — requisitions + relief requests (flagged) 2026-06-22 18:22:59 +05:30
signoff.test.ts feat(crewing): Phase 4c — sign-off & experience (flagged) 2026-06-22 21:34:29 +05:30
vendor-approval.test.ts test(integration): green the last 3 behavioural-drift tests (108/108) 2026-06-21 02:39:41 +05:30
verification.test.ts feat(crewing): Phase 5a — verification queue (flagged) 2026-06-22 21:59:31 +05:30